TRANSMITTAL LETTER FOR BOARD MEETING OF MARCH 5, 2026
COMMITTEE ON ENGINEERING
Mr. John P. Murray, Executive Director
Title
Report on change orders authorized and time extensions approved by the Director of Engineering during the month of January 2026
Body
Dear Sir:
There were eight change orders approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during January 2026.
There were no time extension requests approved by the Director of Engineering for January 2026.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, GCR
Attachments