TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 2, 2018
COMMITTEE ON PROCUREMENT
Mr. John P. Murray, Acting Executive Director
Title
Authority to advertise Contract 18-055-11 Furnish and Deliver Pipe Covering and Insulation to Various Locations for a One (1) Year Period, estimated cost $28,000.00, Account 101-20000-623170
Body
Dear Sir:
Contract documents and specifications have been prepared to furnish and deliver pipe covering and insulation to various locations for a one (1) year period, beginning approximately December 1, 2018 and ending November 30, 2019.
The purpose of this contract is to furnish and deliver pipe covering and insulation to the District’s storerooms, to maintain sufficient inventory levels that are required for the day to day operational needs of the District.
The estimated cost for this contract is $28,000.00.
No bid deposit is required for this contract.
The Multi-Project Labor Agreement (MPLA) is not applicable to this contract because it is primarily a furnish and deliver contract.
The Affirmative Action Ordinance, Revised Appendix D is not included in this contract because it is primarily a furnish and deliver contract.
The tentative schedule for this contract is as follows:
Advertise August 22, 2018
Bid Opening September 11, 2018
Award November 1, 2018
Completion November 30, 2019
Funds are available in Account 101-20000-623170.
In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 18-055-11.
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:MS:np
Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 2, 2018