TRANSMITTAL LETTER FOR BOARD MEETING OF OCTOBER 15, 2026
COMMITTEE ON ENGINEERING
Mr. John P. Murray, Executive Director
Title
Report on change orders authorized and time extensions approved by the Director of Engineering during the month of September 2026
Body
Dear Sir:
There were fifteen change orders approved by the Director of Engineering on contracts with a 5 percent contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during September 2026.
There was one time extension request approved by the Director of Engineering for September 2026.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, JK