RESOLUTION FOR BOARD MEETING OF MARCH 4, 2021
Title
RESOLUTION Adopting a Schedule for the Execution and Completion of the Flood Control Project on Midlothian Creek in Robbins, Cook County, Illinois, Contract 14-253-5C, and Authorizing the Immediate Vesting of Title to Real Estate for the Execution Thereof
Body
WHEREAS, on March 15, 2018 the Board of Commissioners (“the Board”) adopted Ordinance R18-002 establishing the right-of-way for the construction, operation, and maintenance of the Flood Control Project on Midlothian Creek in Robbins, Cook County, Illinois (Contract 14-253-5C) (“Project”);
WHEREAS, the Board determines that completion of the Project in accordance with the schedule adopted by the Board herein is necessary and essential to the public interest and is required for the public health, welfare, and safety and to properly discharge the public duties, powers, and responsibilities of the District;
WHEREAS, the Executive Director has reported that the District has either been unable to identify the owners or reach an agreement as to the acquisition terms and price through direct negotiations with the respective owners of certain of the remaining parcels of the real estate involved;
NOW, THEREFORE, BE IT RESOLVED by the Board of Commissioners of the Metropolitan Water Reclamation District of Greater Chicago:
Section 1. That the Board adopt the following schedule and plan of operation for the execution and completion of construction in two phases, designated Phase 1 and Phase 2, of the Flood Control Project on Midlothian Creek in Robbins, Cook County, Illinois (Contract 14-253-5C):
Phase 1
a. Acquisition of Right-of-Way: August 23, 2021
b. Advertise for Bids: September 6, 2021
c. Award Contract: December 6, 2021
d. Start of Construction: December 27, 2021
e. Completion of Construction: March 22, 2023
Phase 2
a. Acquisition of Right-of-Way: October 22, 2021
b. Advertise for Bids: November 22, 2021
c. Award Contract: February 22, 2022
d. Start of Construction: March 15, 2022
e. Completion of Construction: June 6, 2023
Section 2. That it is hereby found and determined that it is necessary to take or acquire the fee simple title or such lesser interests, as appropriate, in and to the property constituting the right-of-way set forth in Ordinance R18-002 immediately, in order to comply with the schedule adopted by the Board herein for the construction, execution, and completion of this Project.
Section 3. That inasmuch as negotiations for the acquisition of said property have proven unsuccessful despite its due diligence, the General Counsel of the Metropolitan Water Reclamation District of Greater Chicago is hereby directed, pursuant to the provisions of Illinois Compiled Statutes Chapter 70, Section 2605/16 and Chapter 735, Act 30, Article 20, Section 20-5-5 through 20-5-50, to immediately acquire the aforementioned fee simple title or lesser interests, as appropriate.
Section 4. This Resolution shall be in full force and effect from and after its passage.
Dated: March 4, 2021:
Approved:
_______________________________________
Kari K. Steele
President
Board of Commissioners
Metropolitan Water Reclamation District
of Greater Chicago
Approved as to form and legality:
____________________________________
Head Assistant Attorney
____________________________________
General Counsel