TRANSMITTAL LETTER FOR BOARD MEETING OF SEPTEMBER 7, 2023
COMMITTEE ON PROCUREMENT
Mr. Brian A. Perkovich, Executive Director
Title
Authority to award Contract 21-863-2C, Master Plan for Salt Creek at Fullersburg Woods, to V3 Construction Group, LTD., in an amount not to exceed $9,375,745.00, plus a five (5) percent allowance for change orders in an amount of $468,787.25, for a total amount not to exceed $9,844,532.25, Account 201-50000-612400, Requisition 1599071
Body
Dear Sir:
On May 18 ,2023, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise for bids, Contract 21-863-2C, Master Plan for Salt Creek at Fullersburg Woods.
In response to a public advertisement of June 21, 2023, a bid opening was held on July 25, 2023. The bid tabulation for this contract is:
V3 CONSTRUCTION GROUP, LTD $9,375,745.00
F.H. PASCHEN, SN NIELSEN & ASSOCIATES LLC $15,549,000.00
V3 Construction Group, LTD., the lowest responsible bidder, is proposing to perform the contract in accordance with the specifications. The estimated cost range for this contract is $5,709,500.00 to $6,911,500.00, placing their bid of $9,375,745.00 approximately 35.6 percent over the high end of the cost estimate.
The Minority Business Enterprise (MBE), Women Business Enterprise (WBE) and Veteran-Owned Business Enterprise (VBE) utilization goals for this contract are 20 percent MBE, 9 percent WBE, and 3 percent VBE.
V3 Construction Group, LTD., is in compliance with the Affirmative Action Ordinance, Revised Appendix D and Appendix V as indicated on the attached report. The bidder has committed to the following utilization goals for this contract: 20.27 percent MBE, 10.13 percent WBE. Bidder provided 3.04 percent participation for the VBE.
The contract will require approximately thirty-two (32) people for the services.
In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to award Contract 21-863-2C to V3 Construction Group, LTD., in an amount not to exceed $9,375,745.00, plus a five (5) percent allowance for change orders in an amount of $468,787.25, for a total amount not to exceed $9,844,532.25, subject to the contractor furnishing a performance bond in form satisfactory to the Law Department and approved by the Director of Procurement and Materials Management.
The contract specifications require that all work commence 1 day after approval of the contractor’s bond and shall be completed within 1825 calendar days thereafter.
Funds are available in account 201-50000-612400.
V3 Construction Group, LTD., has indicated that they will comply with the DuPage County Forest Preserve Ordinances 22-232 and 20-266 during the life of the contract.
Requested, Catherine A. O’Connor, Director of Engineering
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:af
Respectfully Submitted, Marcelino Garcia, Chairman Committee on Procurement