Skip to main content


To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 23-0771    Version: 1
Type: Report Status: Filed
File created: 7/28/2023 In control: Procurement Committee
On agenda: 8/10/2023 Final action: 8/10/2023
Title: Report of bid opening of Tuesday, July 25, 2023

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 10, 2023

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Report of bid opening of Tuesday, July 25, 2023

Body

 

Dear Sir:

 

Bids were received and opened on 7/25/2023 for the following contracts:

 

CONTRACT 21-863-2C MASTER PLAN FOR SALT CREEK AT FULLERSBURG WOODS

LOCATION:  SALT CREEK, FULLERSBURG WOODS

ESTIMATE:  $6,010,012.00

GROUP: TOTAL 

                     V3 CONSTRUCTION GROUP, LTD.                                                                 $9,375,745.00

                     F.H. PASCHEN, SN NIELSEN & ASSOCIATES LLC                     $15,549,000.00

 

CONTRACT 22-875-1S TELEVISION INSPECTION AND RECORDING OF SEWERS AND MANHOLES AT VARIOUS LOCATIONS

LOCATION:  VARIOUS

ESTIMATE:  $5,520,000.00

GROUP: TOTAL 

                     NATIONAL POWER RODDING CORPORATION                               $7,525,000.00

 

CONTRACT 23-904-22 FURNISHING AND DELIVERING HARMONIC FILTERS TO THE STICKNEY WATER RECLAMATION PLANT (RE-BID)

LOCATION:  STICKNEY, IL

ESTIMATE:  $367,450.00

GROUP: TOTAL 

                     MCDONAGH DEMOLITION, INC.                                                                         $508,300.00

 

Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management