TRANSMITTAL LETTER FOR BOARD MEETING OF MAY 3, 2018
COMMITTEE ON PROCUREMENT
Mr. David St. Pierre, Executive Director
Title
Report of bid opening of Tuesday, April 24, 2018
Body
Dear Sir:
Bids were received and opened on 4/24/2018 for the following contracts:
CONTRACT 17-987-11 SPECIALTY RAILROAD TRACK SERVICES IN THE STICKNEY SERVICE AREA
LOCATION: STICKNEY, IL
ESTIMATE: $343,600.00
GROUP: TOTAL
TRANCO INDUSTRIAL SERVICES, INC. $282,392.10
SWANSON CONTRACTING CO., INC. $294,385.28
TRACK SERVICE, INC. $353,580.00
BIDDERS NOTIFIED: 47 PLANHOLDERS: 20
CONTRACT 18-110-11 FURNISH AND DELIVER WATER QUALITY METERS AND ACCESSORIES
LOCATION: VARIOUS
ESTIMATE: $32,750.00
GROUP: TOTAL
CHEN, GARNER & STEVENS PARTNERS, LLC D/B/A $32,450.00
EUREKA WATER PROBES
BIDDERS NOTIFIED: 312 PLANHOLDERS: 24
CONTRACT 18-618-12 SPECIALIZED REPAIRS FOR LARGE MOTORS (RE-BID)
LOCATION:
ESTIMATE: $90,000.00
GROUP: TOTAL
MIDWEST SERVICE CENTER LLC $112,112.00
L & S ELECTRIC, INC. $134,234.00
BIDDERS NOTIFIED: 381 PLANHOLDERS: 22
CONTRACT 18-695-11 FURNISH AND DELIVER TEMPERATURE PROBES AND REPLACEMENT BATTERIES
LOCATION: LASMA
ESTIMATE: $75,000.00
GROUP: TOTAL
NO BIDS RECEIVED
BIDDERS NOTIFIED: 770 PLANHOLDERS: 28
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management