Legislation Details

File #: 26-0511    Version: 1
Type: Report Status: Filed
File created: 7/15/2026 In control: Procurement Committee
On agenda: 8/13/2026 Final action: 8/13/2026
Title: Report of bid opening of Tuesday, July 14, 2026

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 13, 2026

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Executive Director

 

Title

Report of bid opening of Tuesday, July 14, 2026

Body

 

Dear Sir:

 

Bids were received and opened on 7/14/2026 for the following contracts:

 

CONTRACT 22-602-21 UNDERGROUND STORAGE TANK IMPROVEMENTS AT VARIOUS LOCATIONS

LOCATION:  VARIOUS

ESTIMATE:  $1,449,000.00

GROUP: TOTAL 

                     CROWNE INDUSTRIES LTD                                                                              $1,004,808.00

                     STENSTROM PETROLEUM SERVICES GROUP             $1,241,303.00

                     K.L.F. ENTERPRISES INC                                                                                       $2,437,250.00

 

 

CONTRACT 26-634-11 SERVICES TO INSPECT AND REPAIR CATHODIC PROTECTION SYSTEMS

LOCATION:  VARIOUS

ESTIMATE:  $650,000.00

GROUP: TOTAL 

                     K2 CORROSION ENGINEERING LLC                                                 $616,550.00

                     PIPING & CORROSION SPECIALTIES INC                                $645,770.00

                     CORROSION RESOURCE GROUP CORP                              $669,250.00

 

CONTRACT 26-915-11 FURNISH, DELIVER, AND CHANGE OUT MEDIA IN THE HYDROGEN SULFIDE REMOVAL VESSELS AT THE STICKNEY WATER RECLAMATION PLANT

LOCATION:  STICKNEY, IL

ESTIMATE:  $1,370,000.00

GROUP: TOTAL 

                     BCE-USA LLC                                                                                                                              $1,692,453.00

                     INDEPENDENT MECHANICAL INDUSTRIES INC              $1,772,695.00

 

Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management