TRANSMITTAL LETTER FOR BOARD MEETING OF OCTOBER 15, 2009
COMMITTEE ON ENGINEERING
Mr. Richard Lanyon, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of September 2009
Body
Dear Sir:
Six change orders were approved by the Director of Engineering that cumulatively, but not individually, increased or decreased the cost of contracts by $10,000.00 or more during September 2009. The contracts and related data are listed in the attached sheet.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Joseph P. Sobanski, Director of Engineering, SAF
Attachment