TRANSMITTAL LETTER FOR BOARD MEETING OF JUNE 17, 2021
COMMITTEE ON PROCUREMENT
Mr. Brian A. Perkovich, Executive Director
Title
Authority to award Contract 21-053-11, Furnish and Deliver Lamps and Emergency Lighting to Various Locations for a One (1) Year Period, Group A to Neher Electric Supply, Inc., in an amount not to exceed $17,000.00 and Group B to Evergreen Supply Co., in an amount not to exceed $13,770.00, Account 101-20000-623070
Body
Dear Sir:
On April 1, 2021, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise for bids, Contract 21-053-11 furnish and deliver lamps and emergency lighting to various locations for a one (1) year period, beginning approximately August 1, 2021 and ending July 31, 2022.
In response to a public advertisement of April 21, 2021, a bid opening was held on May 11, 2021. The bid tabulation for this contract is:
GROUP A: LAMPS
NEHER ELECTRIC SUPPLY, INC. $17,000.00
HELSEL-JEPPERSON ELECTRICAL, INC. $18,355.29
EVERGREEN SUPPLY CO. $19,437.50
GROUP B: EMERGENCY LIGHTS
EVERGREEN SUPPLY CO. $13,770.00
HELSEL-JEPPERSON ELECTRICAL, INC. $14,177.00
Neher Electric Supply, Inc., the lowest responsible bidder for Group A, is proposing to perform the contract in accordance with the specifications. The estimated cost for Group A of this contract was $16,000.00, placing the total bid of $17,000.00 approximately 6.3 percent above the estimate.
Evergreen Supply Co., the lowest responsible bidder for Group B, is proposing to perform the contract in accordance with the specifications. The estimated cost for Group B of this contract was $15,000.00 placing the total bid of $13,770.00 approximately 8.2 percent below the estimate.
The Multi-Project Labor Agreement (MPLA) is not applicable to this contract because it is primarily a furnish and deliver contract.
The Affirmative Action Ordinance, Revised Appendix D applies only to construction contracts over a $100,000.00 threshold. These sections on page D-5 of the Ordinance address the types of covered contracts:
• Section 4, Coverage: The following provisions, to be known as "Appendix D" together with relevant forms shall apply and be appended to every construction contract awarded by the District where the estimated total expenditure is in excess of $100,000.00, except contracts let in the event of an emergency contract pursuant to 70 ILCS 2605/11.5."
• Section 5. Definitions: (g) "Construction contract" means any District contract or amendment thereto, providing for a total expenditure in excess on One Hundred Thousand Dollars ($100,000.00) for the construction, demolition, replacement, major repair or renovation and maintenance of real property and improvement thereon or sludge hauling and any other related contract which the District deems appropriate to be subject to Appendix D consistent with the Ordinance.
In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to award Contract 21-053-11, Group A to Neher Electric Supply, Inc., in an amount not to exceed $17,000.00 and Group B, to Evergreen Supply Co., in an amount not to exceed $13,770.00.
Purchase orders will be issued for the material as required. Payment will be based on the unit cost as indicated in the contract documents. No bid deposit is required for this contract. Funds are available in Account 101-20000-623070.
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:MS:cc
Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for June 17, 2021
Attachments