TRANSMITTAL LETTER FOR BOARD MEETING OF JANUARY 23, 2025
 
COMMITTEE ON PROCUREMENT
 
Mr. Brian A. Perkovich, Executive Director
 
Title
Report of bid opening of Tuesday, January 14, 2025
Body
 
Dear Sir:
 
Bids were received and opened on 1/14/2025 for the following contracts:
 
CONTRACT 20-087-3P CHEMICAL PHOSPHORUS REMOVAL, OWRP
LOCATION:  TERRENCE J. O'BRIEN WATER RECLAMATION PLANT
ESTIMATE:  $19,306,724.40
GROUP: TOTAL  
                     IHC CONSTRUCTION COMPANIES, LLC                     $14,226,000.00
                     JOHN BURNS CONSTRUCTION COMPANY LLC                     $14,587,000.00
                     JOSEPH J. HENDERSON & SON, INC.                     $15,874,000.00
 
CONTRACT 25-646-51 SMALL STREAMS MAINTENANCE IN COOK COUNTY, ILLINOIS
LOCATION:  COOK COUNTY
ESTIMATE:  $3,890,000.00
GROUP: TOTAL  
                     J & L CONTRACTORS, INC.                     $3,794,745.00
                     K.L.F. ENTERPRISES, INC.                     $10,941,950.00
                     JUDLAU CONTRACTING, INC.                     $23,392,680.00
 
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management