File #: 08-1524    Version: 1
Type: Agenda Item Status: Adopted
File created: 6/12/2008 In control: Procurement Committee
On agenda: 6/19/2008 Final action: 6/19/2008
Title: Authority to increase Contract 04-294-3M, Calumet TARP Valve Isolation and Pump Station Improvements, Calumet Water Reclamation Plant, to Kenny Construction Company, in an amount of $108,904.08, from an amount of $59,422,110.14 to an amount not to exceed $59,531,014.22, Account 401-50000-645600, Purchase Order 5000309
Attachments: 1. CO 04-294-3M

TRANSMITTAL LETTER FOR BOARD MEETING OF JUNE 19, 2008

 

COMMITTEE ON PURCHASING

 

Mr. Richard Lanyon, General Superintendent

 

Title

Authority to increase Contract 04-294-3M, Calumet TARP Valve Isolation and Pump Station Improvements, Calumet Water Reclamation Plant, to Kenny Construction Company, in an amount of $108,904.08, from an amount of $59,422,110.14 to an amount not to exceed $59,531,014.22, Account 401-50000-645600, Purchase Order 5000309

Body

 

Dear Sir:

 

On December 2, 2004, the Board of Commissioners passed an order authorizing the Purchasing Agent to award Contract 04-294-3M, to Kenny Construction Company, in an amount not to exceed $57,126,700.00.  The contract expires on June 23, 2008. 

 

As of June 6, 2008, the attached list of Change Orders has been approved. The effect of these Change Orders resulted in an increase in the amount of $2,295,410.14 from the original amount awarded of $57,126,700.00. The current contract value is $59,422,110.14. The approved Change Orders reflect a 4.02% increase to the original contract value.

 

The contract includes the replacement of 13.2 KV indoor switchgear in the TARP East and West Electrical Rooms, at the Calumet WRP.  During the installation of the switchgear, a discrepancy was noted in the contract documents, which indicated remote control of the switchgear throughout the distributed control system, but failed to account for it in the switchgear design.  The remote control of the switchgear provides a safer operation for District personnel.  Therefore, a change order is necessary to install control devices for the 13.2 KV switchgear in both the East and West Electrical Rooms. 

 

The contractor submitted a cost proposal (COR-060) in the amount of $108,904.08. The Engineer reviewed the proposal, found it reasonable, and stated via file letter 815 that the Engineering Department would recommend its approval.

 

The Change Order is in compliance with the Illinois Criminal Code, since this Change Order is germane to the original contract.

 

It is hereby requested that the Board of Commissioners authorize the Purchasing Agent to execute a Change Order to increase Contract 04-294-3M in an amount of $108,904.08 (0.18% of the current contract value) from an amount of $59,422,110.14 to an amount not to exceed $59,531,014.22.

 

Funds are available in Account 401-50000-645600.

 

Requested, Joseph P. Sobanski, Chief Engineer, JPS:TEK:JAW

Recommended, Darlene A. LoCascio, Purchasing Agent     

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Purchasing

ORDERED passed by affirmative roll call vote of a majority of the Commissioners present this June 19, 2008.  Approved, President Terrence J. O’Brien

 