TRANSMITTAL LETTER FOR BOARD MEETING OF NOVEMBER 7, 2019
 
COMMITTEE ON PROCUREMENT
 
Mr. Brian A. Perkovich, Executive Director
 
Title
Report of bid opening of Tuesday, October 22, 2019
Body
 
Dear Sir:
 
Bids were received and opened on 10/22/2019 for the following contracts:
 
CONTRACT 19-603-21 FURNISH, DELIVER AND INSTALL MOTOR EXCITATION CONTROL EQUIPMENT AT VARIOUS LOCATIONS
LOCATION:  VARIOUS
ESTIMATE:  $680,000.00
GROUP: TOTAL  
                     BROADWAY ELECTRIC, INC.                     $814,900.00
 
                     BIDDERS NOTIFIED:  1053                     PLANHOLDERS:  24
 
CONTRACT 19-641-11 FURNISHING AND DELIVERING LIQUID CARBON DIOXIDE TO THE STICKNEY WATER RECLAMATION PLANT
LOCATION:  STICKNEY, IL
ESTIMATE:  $930,000.00
GROUP: TOTAL  
                     AIR PRODUCTS & CHEMICALS, INC.                     $882,000.00
                     AMERICAN WELDING & GAS, INC,                      $1,323,000.00
 
                     BIDDERS NOTIFIED:  286                     PLANHOLDERS:  12
 
CONTRACT 19-847-11 TRUCK HAULING OF LIQUID SLUDGE FROM THE LEMONT WATER RECLAMATION PLANT
LOCATION:  LEMONT, IL
ESTIMATE:  $347,100.00
GROUP: TOTAL  
                     SYNAGRO CENTRAL, LLC                     $336,892.50
 
                     BIDDERS NOTIFIED:  401                     PLANHOLDERS:  12
 
CONTRACT 20-045-11 PUBLISH INVITATIONS TO BID FOR CONTRACTS, LEGAL NOTICES FOR ORIGINAL ENTRANCE AND PROMOTIONAL CIVIL SERVICE EXAMINATIONS, AND OTHER LEGAL NOTICES FOR A ONE-YEAR PERIOD
LOCATION:  MOB
ESTIMATE:  $56,000.00
GROUP: TOTAL  
                     SUN-TIMES MEDIA PRODUCTIONS, LLC                     $56,000.00
                     TRIBUNE PUBLISHING COMPANY. LLC                     $63,000.00
 
                     BIDDERS NOTIFIED:  111                     PLANHOLDERS:  5
 
Respectfully Submitted, Darlene A. LoCascio, Director of Procurement and Materials Management