TRANSMITTAL LETTER FOR BOARD MEETING OF DECEMBER 1, 2022
COMMITTEE ON ENGINEERING
Mr. Brian A. Perkovich, Executive Director
Title
Report on change orders authorized and time extensions approved by the Director of Engineering during the month of October 2022
Body
Dear Sir:
There were three change orders approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during October 2022.
There were no time extension requests approved by the Director of Engineering for October 2022.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, GCR