TRANSMITTAL LETTER FOR BOARD MEETING OF APRIL 18, 2019
COMMITTEE ON ENGINEERING
Mr. Brian A. Perkovich, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of March 2019
Body
Dear Sir:
Two change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during March 2019. The contracts and related data are listed in Attachment 1.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, MVL