File #: 24-0820    Version: 1
Type: Agenda Item Status: Adopted
File created: 9/9/2024 In control: Procurement Committee
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Authority to increase Contract 17-134-3MR Odor Control Facilities at Sludge Concentration, Southwest Coarse Screen, Overhead Weir, and Post-Centrifuge Building at the Stickney Water Reclamation Plant, Rebid to IHC Construction Companies, L.L.C. in an amount of $25,085.50, from an amount of $17,308,972.22, to an amount not to exceed $17,334,057.72, Account 401-50000-645650, Purchase Order 4000071
Attachments: 1. Change Order Log - Purchase Order 4000071

TRANSMITTAL LETTER FOR BOARD MEETING OF SEPTEMBER 19, 2024

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Authority to increase Contract 17-134-3MR Odor Control Facilities at Sludge Concentration, Southwest Coarse Screen, Overhead Weir, and Post-Centrifuge Building at the Stickney Water Reclamation Plant, Rebid to IHC Construction Companies, L.L.C. in an amount of $25,085.50, from an amount of $17,308,972.22, to an amount not to exceed $17,334,057.72, Account 401-50000-645650, Purchase Order 4000071

Body

 

Dear Sir:

 

On September 5, 2019, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 17-134-3MR Odor Control Facilities at Sludge Concentration, Southwest Coarse Screen, Overhead Weir, and Post-Centrifuge Building at the Stickney Water Reclamation Plant, Rebid to IHC Construction Companies, L.L.C., in an amount not to exceed $16,485,000.00, plus a five (5) percent allowance for change orders in an amount of $824,250.00, for a total amount not to exceed $17,309,250.00. The scheduled contract completion date is January 3, 2025.

 

As of September 6, 2024, the attached list of change orders has been approved.

 

Original Contract Amount                                                               $16,485,000.00

Date of Board Approval                                                               9/5/2019

Cumulative Change Order (9/6/2024)                     $823,972.22

% Change of Original Contract Value                                          5.00%

Current Contract Value                                                               $17,308,972.22

Requested Increase                                                                                    $25,085.50

New Contract Value                                                                                    $17,334,057.72

% Change of Current Contract Value                                          0.14%

Total % Change of Original Contract Value                     5.15%

 

This amendment is required to address the malfunction of the odor control humidifier sump level sensors and transmitters in the Sludge Bio-Filter Building , Southwest Coarse Screen Bio-Filter Building  and Post-Centrifuge Bio-Filter Building. The level sensors were improperly subjected to a high-pressure water misted environment where two of the three instruments malfunctioned from water intrusion; therefore, new level instruments are required to reduce the risk of future water damage. The contractor submitted a cost proposal (CO-35) for an extra in the amount of $25,085.50. The engineer reviewed the proposal, found it to be reasonable, and stated via correspondence CO35, that the Engineering Department would recommend its approval.

 

This change order is in compliance with the Illinois Criminal Code since the change is germane to the contract.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 17-134-3MR in an amount of $25,085.50 (0.14% of the current contract value), from an amount of $17,308,972.22, to an amount not to exceed $17,334,057.72.

 

Funds are available in Account 401-50000-645650.

 

Requested, Catherine A. O’Connor, Director of Engineering, PO’B:DS

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Marcelino Garcia, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for September 19, 2024

 