Title: Authority to increase Contract 13-248-5F, Streambank Stabilization Project on Melvina Ditch in Oak Lawn and Chicago Ridge, CSA, to Rausch Infrastructure, L.L.C., in an amount of $35,467.86, from an amount of $11,969,547.79 to an amount not to exceed $12,005,015.65, Account 501-50000-645720, Purchase Order 4000076
Attachments: 1. Change Order Log - Purchase Order 4000076

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 10, 2023

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director                    

 

Title

Authority to increase Contract 13-248-5F, Streambank Stabilization Project on Melvina Ditch in Oak Lawn and Chicago Ridge, CSA, to Rausch Infrastructure, L.L.C., in an amount of $35,467.86, from an amount of $11,969,547.79 to an amount not to exceed $12,005,015.65, Account 501-50000-645720, Purchase Order 4000076

Body

 

Dear Sir:

 

On April 16, 2020, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 13-248-5F, Streambank Stabilization Project on Melvina Ditch in Oak Lawn and Chicago Ridge, CSA, to Rausch Infrastructure, L.L.C., in an amount not to exceed $9,847,000.00, plus a five (5) percent allowance for change orders in an amount of $492,350.00, for a total amount not to exceed $10,339,350.00. The contract was substantially completed on June 24, 2022.

 

As of July 14, 2023, the attached list of change orders has been approved.

 

Original Contract Amount                     $9,847,000.00

Date of Board Approval                     4/16/2020

Cumulative Change Orders (7/14/2023)                     $2,122,547.79

% Change of Original Contract Value                     21.56%

Current Contract Value                     $11,969,547.79

Requested Increase                      $35,467.86

New Contract Value                     $12,005,015.65

% Change of Current Contract Value                     0.30%

Total % Change of Original Contract Value                     21.92%

 

During the bid period for Contract 13-248-5F, the contractor asked if the District had information regarding flow rates in Melvina Ditch in an attempt to size an appropriate dewatering system for the creek. The District responded that flows in the creek were an annual average of 4 cubic feet per second (cfs), primarily dictated by intermittent operation of two 7.8 cfs dewatering pumps at the upstream Melvina Ditch Reservoir. Following the bid period and under a separate contract, the District replaced existing pumps at the Melvina Ditch Reservoir with upsized 9.8 cfs pumps. During the duration of construction, the contractor was required to increase the capacity of their as-bid dewatering system to bypass stream flows from the upstream reservoir. The contractor submitted a cost proposal (COR-21) for an extra in the amount of $55,862.66 for an upsized pumping system and a credit for the as-bid pumping system in the amount of $20,394.80, for a net extra in an amount of $35,467.86. The engineer reviewed the proposal, found it acceptable, and recommends its approval.

 

This change order is in compliance with the Illinois Criminal Code since the change is due to circumstances not reasonably foreseen at the time the contract was and is in the best interest of the District.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 13-248-5F in an amount of $35,467.86 (0.30 percent of the current contract value), from an amount of $11,969,547.79 to an amount not to exceed $12,005,015.65.

 

Funds are available in Account 501-50000-645720.

 

Requested, Catherine A. O’Connor, Director of Engineering, KMF:JK

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Marcelino Garcia, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 10, 2023

 

Attachment