Skip to main content


To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 25-0873    Version: 1
Type: Agenda Item Status: PC Increase PO/Change Order
File created: 11/14/2025 In control: Procurement Committee
On agenda: 11/20/2025 Final action:
Title: Authority to increase Contract 08-174-3D Battery A Improvements and Battery B Installation of Mechanical Mixers, SWRP, to IHC Construction Companies, LLC in an amount of $1,120,000.00, from an amount of $56,449,000.00, to an amount not to exceed $57,569,000.00, Account 401-50000-645750, Purchase Order 4000122
Attachments: 1. Change Order Log - Purchase Order 4000122
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TRANSMITTAL LETTER FOR BOARD MEETING OF NOVEMBER 20, 2025

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Acting Executive Director

 

Title

Authority to increase Contract 08-174-3D Battery A Improvements and Battery B Installation of Mechanical Mixers, SWRP, to IHC Construction Companies, LLC in an amount of $1,120,000.00, from an amount of $56,449,000.00, to an amount not to exceed $57,569,000.00, Account 401-50000-645750, Purchase Order 4000122

Body

 

Dear Sir:

 

On December 5, 2024, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 08-174-3D Battery A Improvements and Battery B Installation of Mechanical Mixers, SWRP, to IHC Construction Companies, LLC in an amount not to exceed $56,449,000.00, plus a five (5) percent allowance for change orders in an amount of $2,822,450.00, for a total amount not to exceed $59,271,450.00. The scheduled contract completion date is August 25, 2027.

 

As of November 7, 2025, no change orders have been approved.

 

Original Contract Amount                     $56,449,000.00

Date of Board Approval                     12/5/2024

Cumulative Change Order (11/7/2025)                     $0.00

% Change of Original Contract Value                     0.0%

Current Contract Value                     $56,449,000.00

Requested Increase                     $1,120,000.00

New Contract Value                     $57,569,000.00

% Change of Current Contract Value                     1.98%

Total % Change of Original Contract Value                     1.98%

 

The engineer determined the amount of material required to be removed from the channels and aeration tanks to perform contract work will exceed the quantities estimated in the contract documents by approximately 550 cubic yards. The contractor submitted a cost proposal (CO-02) for all labor, supervision, tools, and equipment for this work for an extra in the amount of $440,000.00 and a credit in the amount of $0.00, for a net extra in the amount of $440,000.00. Subsequent to receiving the contractor’s cost proposal, it was discovered that additional material would be required to be removed from Battery A channels during the battery shutdowns and that the previous estimate was too low. The estimate for the total additional material to be removed was revised to 1,400 cubic yards and a counterproposal for an amount not to exceed $1,120,000.00 was issued and accepted by the contractor. It was stated via correspondence CO02 that the Engineering Department would recommend its approval.

 

The above change order is in compliance with the Illinois Criminal Code since the change is germane to the contract as signed.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 08-174-3D in an amount of $1,120,000.00 (1.98% of the current contract value), from an amount of $56,449,000.00, to an amount not to exceed $57,569,000.00.

 

Funds are available in Account 401-50000-645750.

 

Requested, Catherine A. O’Connor, Director of Engineering, CS:GAK:JB

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Precious Brady-Davis, Chairperson Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for November 20, 2025