To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 24-0864    Version: 1
Type: Agenda Item Status: Adopted
File created: 9/24/2024 In control: Procurement Committee
On agenda: 10/3/2024 Final action: 10/3/2024
Title: Authority to increase Contract 18-254-3P Chemical Phosphorus Removal Facility, Calumet Water Reclamation Plant, to IHC Construction Companies, LLC in an amount of $84,470.20, from an amount of $16,435,823.26, to an amount not to exceed $16,520,293.46, Account 201-50000-645650, Purchase Order 4000092
Attachments: 1. Change Order Log - Purchase Order 4000092.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF OCTOBER 3, 2024

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director                    

 

Title

Authority to increase Contract 18-254-3P Chemical Phosphorus Removal Facility, Calumet Water Reclamation Plant, to IHC Construction Companies, LLC in an amount of $84,470.20, from an amount of $16,435,823.26, to an amount not to exceed $16,520,293.46, Account 201-50000-645650, Purchase Order 4000092

Body

 

Dear Sir:

 

On August 11, 2022, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 18-254-3Pr Chemical Phosphorus Removal Facility, Calumet Water Reclamation Plant, to IHC Construction Companies, LLC in an amount not to exceed $15,577,000.00, plus a five (5) percent allowance for change orders in an amount of $778,850.00, for a total amount not to exceed $16,355,850.00. The scheduled contract completion date is November 29, 2024.

 

As of September 20, 2024, the attached list of change orders has been approved.

 

Original Contract Amount                     $15,577,000.00

Date of Board Approval                     8/11/2022

Cumulative Change Order (9/20/2024)                     $858,823.26

% Change of Original Contract Value                     5.51%

Current Contract Value                     $16,435,823.26

Requested Increase                     $84,470.20

New Contract Value                     $16,520,293.46

% Change of Current Contract Value                     0.51%

Total % Change of Original Contract Value                     6.06%

 

Item 1. The contractor submitted a cost proposal (CO-37) for providing material and labor for installing additional wiring, conduits, and supports to reach instrumentation located on the south faces of chemical storage tanks in the amount of $65,231.10. The engineer reviewed the proposal, found it to be reasonable, and stated via correspondence CO37, that the Engineering Department would recommend its approval.

 

Item 2. The contractor submitted a cost proposal (CO-39) for providing material and labor for drilling additional bolts into an access hatch in 6th Street to prevent wastewater from leaking out of the hatch and onto the street, in the amount of $1,605.00. The engineer reviewed the proposal, found it to be reasonable, and stated via correspondence CO39, that the Engineering Department would recommend its approval.

 

Item 3. The contractor submitted a cost proposal (CO-41) for providing material and labor for installing sixteen (16) additional relays in the DCS cabinets inside the phosphorus pumping buildings for the currently supplied model of high-level switches to be compatible with the DCS system, in the amount of $17,634.10. The engineer reviewed the proposal, found it to be reasonable, and stated via correspondence CO41, that the Engineering Department would recommend its approval.

 

The above change orders are in compliance with the Illinois Criminal Code since the changes are germane to the contract.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute these change orders to increase Contract 18-254-3P in an amount of $84,470.20 (0.51% of the current contract value), from an amount of $16,435,823.26, to an amount not to exceed $16,520,293.46.

 

Funds are available in Account 201-50000-645650.

 

Requested, Catherine A. O’Connor, Director of Engineering, PO’B

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Marcelino Garcia, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for October 3, 2024

 