TRANSMITTAL LETTER FOR THE BOARD MEETING OF APRIL 5, 2018
COMMITTEE ON FINANCE
Mr. David St. Pierre, Executive Director
Title
Authority to add Project 18-915-21, Furnish and Deliver an Articulating Boom Lift to the Stickney Water Reclamation Plant, to the Construction Fund, estimated cost of the project is $70,000.00
Body
Dear Sir:
Authority is requested to add Project 18-915-21, Furnish and Deliver an Articulating Boom Lift to the Stickney Water Reclamation Plant, to the Construction Fund at the request of the Maintenance and Operations Department.
The purpose of the project is to furnish and deliver one diesel-powered, four wheel drive, articulating boom lift, with accessories. The new lift is to allow plant personnel to work on equipment and facilities off-road, such as high line conveyance systems and TARP structure antennas.
The project consists of furnishing and delivering an articulating boom lift to the Stickney Water Reclamation Plant. The estimated cost of the project is $70,000.00.
Requested, John P. Murray, Director of Maintenance and Operations, BAP:SO’C:MAG:JR
Respectfully Submitted, Frank Avila, Chairman Committee on Finance
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for April 5, 2018