Skip to main content


To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 25-0865    Version: 1
Type: Report Status: To Be Introduced
File created: 11/12/2025 In control: Engineering Committee
On agenda: 11/20/2025 Final action:
Title: Report on change orders authorized and time extensions approved by the Director of Engineering during the month of October 2025
Attachments: 1. Attachment 1 CO Report October 2025 5% Contingency - Final.pdf, 2. Attachment 2 CO Status Report October 2025 - FINAL.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TRANSMITTAL LETTER FOR BOARD MEETING OF NOVEMBER 20, 2025

 

COMMITTEE ON ENGINEERING

 

Mr. John P. Murray, Acting Executive Director

 

Title

Report on change orders authorized and time extensions approved by the Director of Engineering during the month of October 2025

Body

 

Dear Sir:

 

There were eight change orders approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during October 2025.

 

There were no time extension requests approved by the Director of Engineering for October 2025.

 

Please advise the undersigned if additional information is required.

 

Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, GCR

 