TRANSMITTAL LETTER FOR BOARD MEETING OF SEPTEMBER 21, 2023
COMMITTEE ON ENGINEERING
Mr. Brian A. Perkovich, Executive Director
Title
Report on change orders authorized and time extensions approved by the Director of Engineering during the month of August 2023
Body
Dear Sir:
There were four change orders approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during August 2023.
There were no time extension requests approved by the Director of Engineering for August 2023.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, GCR
Attachments