File #: 08-2519    Version: 1
Type: Agenda Item Status: Adopted
File created: 12/10/2008 In control: Procurement Committee
On agenda: 12/18/2008 Final action: 12/18/2008
Title: Authority to advertise Contract 09-983-11 Furnish, Deliver and Install a Liquid Carbon Dioxide Storage Tank and Feed System at the Stickney Water Reclamation Plant, estimated cost $250,000.00, Account 101-69000-634650, Requisition 1261139

TRANSMITTAL LETTER FOR BOARD MEETING OF DECEMBER 18, 2008

 

COMMITTEE ON PURCHASING

 

Mr. Richard Lanyon, General Superintendent

 

Title

Authority to advertise Contract 09-983-11 Furnish, Deliver and Install a Liquid Carbon Dioxide Storage Tank and Feed System at the Stickney Water Reclamation Plant, estimated cost $250,000.00, Account 101-69000-634650, Requisition 1261139

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for the procurement of services to furnish, deliver and install a liquid carbon dioxide storage tank and feed system at the Stickney Water Reclamation Plant. The storage tank and feed system will be used to store and provide uninterrupted supply of liquid carbon dioxide needed to inhibit struvite formation in the centrifuges and associated piping. This sludge conditioning process helps to prevent blockages that cause excessive downtime and result in high maintenance costs.

 

The total estimated cost for this contract is $250,000.00.

 

The bid deposit for this contract is $12,500.00.

 

Work under this contract is to commence upon approval of the contractor's bond, and be completed within sixty (60) calendar days thereafter. Liquidated damages are $100.00 per day for each calendar day the contractor fails to perform the specified work, as set forth in the contract documents, and as directed by the Engineer.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

The Revised Appendix D will be included in this contract. The type of work to be performed under the contract is within the “Mechanical” category for establishing PCE utilization goals. The PCE utilization goals for this contract are 20% Minority Business Enterprises (MBE), 9% Women’s Business Enterprises (WBE), and 10% Small Business Enterprises (SBE).

 

The tentative schedule for this contract is as follows:

 

Advertise                                                               January 14, 2009

Bid Opening                                          February 10, 2009

Award                                                                                    April 2, 2009

Completion                                          June 30, 2009

 

Funds are being requested in 2009, in Account 101-69000-634650, and are contingent on the Board of Commissioners’ approval of the District’s budget for that year.

 

In view of the foregoing, it is recommended that the Purchasing Agent be authorized to advertise Contract 09-983-11.

 

Requested, Osoth Jamjun, Chief of Maintenance and Operations, MPS:SO’C:MAG:IJA

Recommended, Darlene A. LoCascio, Purchasing Agent

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Purchasing