TRANSMITTAL LETTER FOR BOARD MEETING OF MARCH 6, 2025
COMMITTEE ON PROCUREMENT
Mr. Brian A. Perkovich, Executive Director
Title
Authority to increase Contract 20-161-3S Salt Creek Intercepting Sewer No. 3 Rehabilitation, SSA, to Inliner Solutions, LLC in an amount of $115,000.00, from an amount of $19,872,654.00, to an amount not to exceed $19,987,654.00, Account 401-50000-645700, Purchase Order 4000120
Body
Dear Sir:
On November 7, 2024, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 20-161-3S Salt Creek Intercepting Sewer No. 3 Rehabilitation, SSA, to Inliner Solutions, LLC (Inliner) in an amount not to exceed $19,872,654.00, plus a five (5) percent allowance for change orders in an amount of $993,632.70, for a total amount not to exceed $20,866,286.70. The scheduled contract completion date is July 27, 2026.
This contract has no prior change orders.
Original Contract Amount $19,872,654.00
Date of Board Approval 11/07/2024
Cumulative Change Order (2/21/2025) $0.00
% Change of Original Contract Value 0.00%
Current Contract Value $19,872,654.00
Requested Increase $115,000.00
New Contract Value $19,987,654.00
% Change of Current Contract Value 0.58%
Total % Change of Original Contract Value 0.58%
Additional scope items are necessary to complete the rehabilitation work including unit price items for injection grouting to stop infiltration prior to the installation of the liner and to repair spalling along the wall and restore sections of the sewer invert, allowing for the sewer lining process to take place. Work will be performed on a fixed unit price basis as needed. The contractor submitted a cost proposal (CO-1) for an extra in the amount of $115,000.00 and a credit in the amount of $0.00, for a net extra in the amount of $115,000.00. The Engineer reviewed the proposal, found it to be reasonable, and stated via correspondence CO1 that the Engineering Department would recommend its approval.
This change order is in compliance with the Illinois Criminal Code since the change is due to circumstances not reasonably foreseeable at the time the contract was signed and is in the best interest of the District.
It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 20-161-3S in an amount of $115,000.00 (0.58% of the current contract value), from an amount of $19,872,654.00, to an amount not to exceed $19,987,654.00.
Funds are available in Account 401-50000-645700.
Requested, Catherine A. O’Connor, Director of Engineering, KMF:LS
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management
Respectfully Submitted, Precious Brady-Davis, Chairperson Committee on Procurement
Disposition of this agenda item will be documented in the Official Regular Board Meeting Minutes of the Board of Commissioners for March 6, 2025
Attachments