File #: 25-0490    Version: 1
Type: Agenda Item Status: Deferred
File created: 6/16/2025 In control: Procurement Committee
On agenda: 7/17/2025 Final action: 7/17/2025
Title: Authority to increase Contract 01-103-AS 39th Street Conduit Rehabilitation - Phase II, SSA, to Michels Trenchless, Inc. in an amount of $1,245,780.90, from an amount of $39,863,453.03, to an amount not to exceed $41,109,233.93, Account 401-50000-645700, Purchase Order 4000119 (Deferred from the June 26, 2025 Board Meeting)
Attachments: 1. Change Order Log - Purchase Order 4000119

TRANSMITTAL LETTER FOR BOARD MEETING OF JULY 17, 2025

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Acting Executive Director                    

 

Title

Authority to increase Contract 01-103-AS 39th Street Conduit Rehabilitation - Phase II, SSA, to Michels Trenchless, Inc. in an amount of $1,245,780.90, from an amount of $39,863,453.03, to an amount not to exceed $41,109,233.93, Account 401-50000-645700, Purchase Order 4000119 (Deferred from the June 26, 2025 Board Meeting)

Body

 

Dear Sir:

 

On October 17, 2024, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 01-103-AS 39th Street Conduit Rehabilitation - Phase II, SSA, to Michels Trenchless, Inc. in an amount not to exceed $39,418,164.03, plus a five (5) percent allowance for change orders in an amount of $1,970,908.20, for a total amount not to exceed $41,389,072.23. The scheduled completion date is November 16, 2026.

 

As of June 6, 2025, the attached list of change orders has been approved.

                      

Original Contract Amount                                                               $39,418,164.03

Date of Board Approval                                                                                   10/17/2024

Cumulative Change Order (6/6/2025)                                      $445,289.00

% Change of Original Contract Value                                           1.13%

Current Contract Value                                                                                  $39,863,453.03

Requested Increase                                                                                     $1,245,780.90                    

New Contract Value                                                                                    $41,109,233.93

% Change of Current Contract Value                                          3.13%

Total % Change of Original Contract Value        4.29%

 

After reviewing the sewer condition, it was found that additional scope items are needed to complete the sewer rehabilitation work effectively, including injection grouting to stop water infiltration prior to lining, spalling rehabilitation in areas where the sewer has severe deterioration, and manhole frame and cover rehabilitation. Work will be performed on a fixed unit price basis as needed for each of these items. The contractor submitted cost proposal (CO-2) for an extra in the amount of $2,708,547.25. The engineer reviewed the proposal and submitted a counterproposal in the amount of $1,245,780.90, which was accepted by the contractor, and stated via correspondence CO02 that the Engineering Department would recommend its approval.

 

This change order is in compliance with the Illinois Criminal Code since the change is due to circumstances not reasonably foreseeable at the time the contract was signed and is in the best interest of the District.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 01-103-AS in an amount of $1,245,780.90 (3.13% of the current contract value), from an amount of $39,863,453.03, to an amount not to exceed $41,109,233.93.

 

Funds are available in Account 401-50000-645700.

 

Requested, Catherine A. O’Connor, Director of Engineering, KMF:LS

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Precious Brady-Davis, Chairperson Committee on Procurement

Disposition of this agenda item will be documented in the Official Regular Board Meeting Minutes of the Board of Commissioners for July 17, 2025

 