File #: 17-0851    Version: 1
Type: Agenda Item Status: Adopted
File created: 8/18/2017 In control: Finance Committee
On agenda: 8/31/2017 Final action: 8/31/2017
Title: Authority to add Project 17-611-21 Furnish and Deliver Uninterruptible Power Supplies for the Kirie and Egan Water Reclamation Plants, to the Construction Fund, estimated cost of the project is $60,000.00

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 31, 2017

 

COMMITTEE ON FINANCE

 

Mr. David St. Pierre, Executive Director

 

Title

Authority to add Project 17-611-21 Furnish and Deliver Uninterruptible Power Supplies for the Kirie and Egan Water Reclamation Plants, to the Construction Fund, estimated cost of the project is $60,000.00

Body

 

Dear Sir:

 

Authority is requested to add Project 17-611-21 Furnish and Deliver Uninterruptible Power Supplies for the Kirie and Egan Water Reclamation Plants, to the Construction Fund, at the request of the Maintenance and Operations Department.

 

The project consists of procuring three uninterruptible power supplies (UPS) for the Kirie and Egan Water Reclamation Plants. The existing units, which support critical distributed control and Monitoring and Research equipment, are failing and not functioning properly.

 

The estimated cost for the project is $60,000.00

 

Requested, John P. Murray, Director of Maintenance and Operations, BAP:SO’C:MAG:JR:JMC

Respectfully Submitted, Frank Avila, Chairman Committee on Finance

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 31, 2017