TRANSMITTAL LETTER FOR BOARD MEETING OF August 31, 2017
COMMITTEE ON FINANCE
Mr. David St. Pierre, Executive Director
Title
Authority to add Project 11-186-AF, Demolition at the Addison Creek Reservoir site in Bellwood, Illinois and at the Thornton Reservoir in South Holland, Illinois to the Engineering Department Capital Improvement Program and the Capital Improvement Bond Fund, estimated cost of the project is $970,000.00
Body
Dear Sir:
Authority is requested to add Project 11-186-AF, Demolition at Addison Creek Reservoir site in Bellwood, Illinois and at the Thornton Reservoir in South Holland, Illinois to the Engineering Department Capital Improvement Program and the Capital Improvements Bond Fund.
The purpose of the project is to demolish three buildings at the Addison Creek Reservoir site to eliminate safety concerns and accommodate the future reservoir construction, and three buildings at the Thornton Reservoir that are no longer needed by the District.
The estimated cost of the project $970,000.00.
Requested, Marcella V. Landis, Acting Director of Engineering, WSS:JK
Respectfully Submitted, Frank Avila, Chairman Committee on Finance
Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 31, 2017
Attachment