TRANSMITTAL LETTER FOR BOARD MEETING OF JANUARY 18, 2018
COMMITTEE ON ENGINEERING
Mr. David St. Pierre, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of December 2017
Body
Dear Sir:
Eight change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during December 2017. The contracts and related data are listed in Attachment 1.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Marcella V. Landis, Acting Director of Engineering, MVL:JFK