Title: Authority to add Project 18-607-31 Cofferdam Installation and Removal at Sluice Gate No. 2 Lockport Controlling Works, to the Bond Fund, estimated cost of the project is $350,000.00

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 2, 2018

 

COMMITTEE ON FINANCE

 

Mr. John P. Murray, Acting Executive Director

 

Title

Authority to add Project 18-607-31 Cofferdam Installation and Removal at Sluice Gate No. 2 Lockport Controlling Works, to the Bond Fund, estimated cost of the project is $350,000.00

Body

 

Dear Sir:

 

Authority is requested to add Project 18-607-31 Cofferdam Installation and Removal at Sluice Gate No.2 Lockport Controlling Works, to the Bond Fund, at the request of the Maintenance and Operations Department.

 

The project consists of installing and removing a temporary cofferdam on the upstream side of the sluiceway of sluice gate No. 2 at the Lockport Controlling Works. This will enable other planned repair work to be performed on the sluice gate. The cofferdam will allow work to be performed under safe conditions and eliminate the possibility of unregulated flow.

 

The estimated cost of the project is $350,000.00

 

Requested, Brett A. Garelli, Acting Director of Maintenance and Operations, BAP:SO’C:MAG:JR:DR

Respectfully Submitted, Frank Avila, Chairman Committee on Finance