TRANSMITTAL LETTER FOR BOARD MEETING OF FEBRUARY 18, 2021
COMMITTEE ON ENGINEERING
Mr. Brian A. Perkovich, Executive Director
Title
Report on change orders authorized and approved by the Director of Engineering during the month of January 2021
Body
Dear Sir:
Four change orders were approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during January 2021. The contracts and related data are listed in Attachment 1 and Attachment 2.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, GCR
Attachments