File #: 21-0204    Version: 1
Type: Agenda Item Status: Adopted
File created: 2/23/2021 In control: Procurement Committee
On agenda: 3/4/2021 Final action: 3/4/2021
Title: Authority to advertise Contract 11-187-AF Demolition for Addison Creek Channel Improvements, SSA, estimated cost between $622,250.00 and $753,250.00, Account 501-50000-645620, Requisition 1558472
Attachments: 1. Contract 11-187-AF Project Fact Sheet.pdf, 2. Contract 11-187-AF Affirmative Action Goals Report

TRANSMITTAL LETTER FOR BOARD MEETING OF MARCH 4, 2021

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Authority to advertise Contract 11-187-AF Demolition for Addison Creek Channel Improvements, SSA, estimated cost between $622,250.00 and $753,250.00, Account 501-50000-645620, Requisition 1558472

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 11-187-AF Demolition for Addison Creek Channel Improvements, SSA. The purpose of this contract is to demolish sixteen (16) residential buildings and thirteen (13) mobile-home trailers in Melrose Park, Northlake, Stone Park, and Bellwood in order to eliminate safety concerns and accommodate construction for the future Addison Creek Channel Improvements project.

 

The engineer’s estimated cost for this contract is between $622,250.00 and $753,250.00.

 

The bid deposit for this contract is $33,000.00.

 

The contract specifications require that all work commence 30 days after approval of the contractor’s bond and shall be completed within 180 calendar days after approval of the contractor’s bond. Liquidated damages are $1,000.00 for each calendar day that the contractor is in default of the time specified for failing to achieve substantial work completion and $200.00 for each calendar day that the contractor is in default of the time specified for completion of the entire work.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D will be included in this contract. The type of work to be performed under the contract is within the “General Construction” category for establishing Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE) and/or Small Business Enterprises (SBE), and/or Veteran-owned Business Enterprises (VBE) utilization goals. The MBE, WBE, SBE, and/or VBE utilization goals for this contract are 20 percent MBE, 10 percent WBE, 10 percent SBE, and 3 percent VBE.

 

The tentative schedule for this contract is as follows:

Advertise                                          March 17, 2021

Bid Opening                                          April 20, 2021

Award                                                               May 20, 2021

Completion                                          November 15, 2021

 

Funds are available in Account 501-50000-645620.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 11-187-AF.

 

Requested, Catherine A. O’Connor, Director of Engineering, KMF:JK

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for March 4, 2021

 