To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 21-0699    Version: 1
Type: Agenda Item Status: Adopted
File created: 7/26/2021 In control: Procurement Committee
On agenda: 8/5/2021 Final action: 8/5/2021
Title: Authority to award Contract 21-025-11, Furnish and Deliver Plumbing Pipe, Fittings and Valves to Various Locations for a One-Year Period, All Groups, to Columbia Pipe & Supply LLC, in an amount not to exceed $340,772.17, Account 101-20000-623090
Attachments: 1. Contract 21-025-11 Item Descriptions - Groups A through J.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 5, 2021

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Authority to award Contract 21-025-11, Furnish and Deliver Plumbing Pipe, Fittings and Valves to Various Locations for a One-Year Period, All Groups, to Columbia Pipe & Supply LLC, in an amount not to exceed $340,772.17, Account 101-20000-623090

Body

 

Dear Sir:

 

On May 20, 2021, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise for bids, Contract 21-025-11 furnish and deliver plumbing pipe, fittings and valves to various locations for a one year period, beginning approximately September 1, 2021 and ending August 31, 2022.

 

In response to a public advertisement of June 9, 2021, a bid opening was held on June 29, 2021. The bid tabulation for this contract is:

 

GROUP A: PIPE

COLUMBIA PIPE & SUPPLY LLC                     *$36,779.39

                     *corrected total

 

GROUP B: Hose Clamps & Couplings

COLUMBIA PIPE & SUPPLY LLC                     *$9,892.54

                     *corrected total

 

GROUP C: VALVES

COLUMBIA PIPE & SUPPLY LLC                     *$172,221.63

                     *corrected total

 

GROUP D: GALVANIZED FITTINGS

COLUMBIA PIPE & SUPPLY LLC                     *$28,045.41

                     *corrected total

 

GROUP E: MALLEABLE IRON FITTINGS

COLUMBIA PIPE & SUPPLY LLC                     *$21,794.04

                     *corrected total

 

GROUP F: STAINLESS STEEL FITTINGS

COLUMBIA PIPE & SUPPLY LLC                     *$3,063.11

                     *corrected total

 

GROUP G: SCHEDULE 40 & 80 FITTINGS

COLUMBIA PIPE & SUPPLY LLC                     *$14,480.52

                     *corrected total

 

GROUP H: FORGED FITTINGS

COLUMBIA PIPE & SUPPLY LLC                     *$10,894.51

                     *corrected total

 

GROUP I: COPPER PIPE, TUBING, & FITTINGS

COLUMBIA PIPE & SUPPLY LLC                     *$31,515.96

                     *corrected total

 

GROUP J: MISCELLANEOUS SUPPLIES

COLUMBIA PIPE & SUPPLY LLC                     *$12,085.06

                     *corrected total

 

The Director of Procurement and Materials Management has reviewed the list of bidders for this contract and is satisfied that the market for this service has been adequately solicited.

 

A survey of plan holders for this contract was done and vendors cited one or more of the following as reasons for not bidding:  unable to bid at this time; not scope of work; unable to supply all materials as per contract requirements.  In light of these findings, the Director of Procurement and Materials Management is of the opinion that the sole bid received is a fair and reasonable price and nothing would be gained by rejecting their proposal and re-advertising this contract.

 

Columbia Pipe & Supply LLC, the sole responsible bidder for all Groups, is proposing to perform the contract in accordance with the specifications. The estimated cost for this contract was $295,000.00, placing the total bid of $340,772.17 approximately 15.52 percent above the estimate.

 

The Multi-Project Labor Agreement (MPLA) is not applicable to this contract because it is primarily a furnish and deliver contract.

 

The Affirmative Action Ordinance, Revised Appendix D applies only to construction contracts over a $100,000.00 threshold. These sections on page D-5 of the Ordinance address the types of covered contracts:

 

                     Section 4, Coverage: The following provisions, to be known as "Appendix D" together with relevant forms shall apply and be appended to every construction contract awarded by the District where the estimated total expenditure is in excess of $100,000.00, except contracts let in the event of an emergency contract pursuant to 70 ILCS 2605/11.5."

 

                      Section 5. Definitions: (g) "Construction contract" means any District contract or amendment thereto, providing for a total expenditure in excess on One Hundred Thousand Dollars ($100,000.00) for the construction, demolition, replacement, major repair or renovation and maintenance of real property and improvement thereon or sludge hauling and any other related contract which the District deems appropriate to be subject to Appendix D consistent with the Ordinance.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to award Contract 21-025-11, all Groups to Columbia Pipe & Supply LLC, in an amount not to exceed $340,772.17.

 

No bid deposit was required for this contract.

 

Purchase orders will be issued for the material as required.  Payment will be based on the unit cost as indicated in the contract documents.  Funds are available in Account 101-20000-623090.

 

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:MS:np

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 5, 2021

 

Attachment