File #: 22-0614    Version: 1
Type: Agenda Item Status: Adopted
File created: 6/30/2022 In control: Procurement Committee
On agenda: 7/14/2022 Final action: 7/14/2022
Title: Authorization to decrease cost estimate and re-advertise Contract 20-859-3SR Drop Shaft Modifications and Collection Facilities Work, NSA, estimated cost between $1,995,000.00 and $2,415,000.00, Account 401-50000-645600, Requisition 1570130
Attachments: 1. Contract 20-859-3SR Affirmative Action Goals Report, 2. Contract 20-859-3SR Supplier's Exception Approval

TRANSMITTAL LETTER FOR BOARD MEETING OF JULY 14, 2022

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Authorization to decrease cost estimate and re-advertise Contract 20-859-3SR Drop Shaft Modifications and Collection Facilities Work, NSA, estimated cost between $1,995,000.00 and $2,415,000.00, Account 401-50000-645600, Requisition 1570130

Body

 

Dear Sir:

 

On October 21, 2021, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise Contract 20-859-3S Drop Shaft Modifications and Collection Facilities Work, NSA, at an estimated cost between $4,512,500.00 and $5,462,500.00,

 

The contract was originally advertised for bid on December 15, 2021. On March 17, 2022, it was reported to the Board of Commissioners that no bids were received for Contract 20-859-3S, Drop Shaft Modifications and Collection Facilities Work, NSA.

 

The decrease in the contract cost estimate is due to the Board’s previously expressed desire to de-bundle contracts when appropriate. The current contract which we are seeking authority to re-advertise has been amended to simplify the scope and include only work related to control structure modifications, grating, and louver installations. A separate contract will be issued for work within the deep tunnel system related to rehabilitation lining, inspections, installation of a transient weir, and other miscellaneous items.

 

Work will consist of the installation of louver systems at Drop Shaft No.’s UDP-DS8 and DS-N19, replacement and repair of gates and accessories at Control Structure 10 and modification of structure on UDP 11A.

 

The necessary right-of-way documents have been acquired.

 

It is estimated that roughly 11 full time equivalent jobs will be created during this contract period.

 

The engineer’s estimated cost for this contract is between $1,995,000.00 and $2,415,000.00. The estimated cost range will be stated in the advertisement for bids.

 

The bid deposit for this contract is $105,000.00.

 

The contract specifications require that all work commence 30 calendar days after approval of the contractor’s bond and shall be completed within 400 calendar days after approval of the contractor’s bond. Liquidated damages are $650.00 for each calendar day beyond the specified date for substantial completion and $200.00 for each calendar day beyond the specified date for final completion.

 

The Multi-Project Labor Agreement will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D will be included in this contract. The work under this contract should be classified as “Construction Services”. The Socially and Economically Disadvantaged goals associated with this contract are Minority-owned Business Enterprise (MBE), Women-owned Business Enterprise (WBE), Small Business Enterprise (SBE), and Veteran-owned Business Enterprise (VBE). The associated goals are: 15% MBE and/or WBE, 10% SBE, and 3% VBE.

 

The tentative schedule for this contract is as follows:

Advertise                                          August 10, 2022

Bid Opening                                            October 4, 2022

Award                                                               December 1, 2022

Completion                                          January 5, 2024

 

Funds are available in Account 401-50000-645600.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 20-859-3SR.

 

Requested, Catherine O’Connor, Director of Engineering, KMF

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for July 14, 2022

 