To watch the live meeting proceedings, please refresh this page at the scheduled meeting time, a link labeled "In Progress" will appear under the Video column
File #: 22-0724    Version: 1
Type: Agenda Item Status: Adopted
File created: 8/3/2022 In control: Procurement Committee
On agenda: 8/11/2022 Final action: 8/11/2022
Title: Authorization to increase cost estimate for Contract 16-127-3DR A/B and C/D Service Tunnel Rehabilitation - Phase Three, Stickney Water Reclamation Plant, estimated cost between $23,845,000.00 and $28,865,000.00, Account 401-50000-645750, Requisition 1567540
Attachments: 1. 16-127-3DR Project Fact Data.pdf, 2. 16-127-3DR Affirmative Action Memo 98% Review.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF AUGUST 11, 2021

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Authorization to increase cost estimate for Contract 16-127-3DR A/B and C/D Service Tunnel Rehabilitation - Phase Three, Stickney Water Reclamation Plant, estimated cost between $23,845,000.00 and $28,865,000.00, Account 401-50000-645750, Requisition 1567540

Body

 

Dear Sir:

 

On September 2, 2021, the Board of Commissioners authorized the Director of Procurement and Materials Management to advertise Contract 16-127-3D A/B and C/D Service Tunnel Rehabilitation - Phase Three, Stickney Water Reclamation Plant at an estimated cost between $16,625,000.00 and $20,125,000.00.

 

The bid opening was November 2, 2021. The sole bid was rejected on December 16, 2021.

 

During the original bidding process, questions were raised that required clarifications and additional work required under the contract documents.  Prior to the re-bid, the District worked with the engineering consultant to revise the contract drawings and specifications to address these issues and to clarify the details of the work.  It is anticipated that these revisions to the documents and drawings should attract more bidders. The cost estimate for the project has been revised to reflect the additional work and to reflect these inflationary increases.

 

The purpose of this project is to perform localized repairs of deteriorated segments of various service tunnel structures within the Stickney Water Reclamation Plant. Some of these structures are over 80 years old and contain utilities vital to plant operations. This project is required to restore the structural integrity of deteriorated concrete slabs, walls, beams and columns, and restore them in such a way to prevent further accelerating deterioration.

 

The project consists of the following:

 

1.      Structurally rehabilitate approximately 1050 lineal feet of the A/B Service Tunnel, 1050 lineal feet of the C/D Service Tunnel, 733 lineal feet of the South R&D Tunnel, 225 lineal feet of the E-W Aerated Grit Tunnel and provide minor repairs on other tunnels.

 

2.      Provide temporary and/or permanent relocation of electrical, mechanical and process utilities inside the tunnels. Remove abandoned electrical conduits and mechanical piping from the tunnels.

 

3.      Install new or repair pipe racks, piping, electrical conduits, lighting, and mechanical equipment in the A/B and C/D Service Tunnels and the South R&D Tunnel.

 

4.      Modify and upgrade the A/B and C/D Service Tunnel ventilation systems, including electrical feeds, fans, ductwork and associated appurtenances. Provide additional temperature control by repairing and insulating Batteries A, B, C and D Air Mains.

 

It is estimated that 120 jobs will be created or saved as a result of award of this contract with an estimated 152,368 man-hours of skilled trades utilized.

 

The estimated cost for this contract is between $23,845,000.00 and $28,865,000.00. The cost range will be stated in the advertisement for bids.

 

The bid deposit for this contract is $600,000.00.

 

The contract specifications require that all work commence 30 calendar days after approval of the contractor’s bond and shall be completed within 1,095 calendar days after approval of the contractor’s bond. Liquidated damages are $1,000.00 for each calendar day that the contractor is in default of the time specified for failing to achieve substantial work completion and $200.00 for each calendar day that the contractor is in default of the time specified for completion of the entire work.

 

The Multi-Project Labor Agreement will be included in this contract.

 

The Affirmative Action Ordinance, Revised Appendix D will be included in this contract. The type of work to be performed under the contract is within the “Construction Services” category for establishing Minority-owned Business Enterprises (MBE), Women-owned Business Enterprises (WBE), Small Business Enterprises (SBE) and Veteran-owned Business Enterprises (VBE) utilization goals. The MBE, WBE, SBE and VBE utilization goals for this contract are: 20 percent MBE, 10 percent WBE, 10 percent SBE and 3 percent VBE.

 

The tentative schedule for this contract is as follows:

Advertise                                          August 31, 2022

Bid Opening                       October 4, 2022

Award                                                               November 3, 2022

Completion                                          November 2, 2025

 

Funds are available in Account 401-50000-645750.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to increase the cost estimate for Contract 16-127-3DR (Re-Bid).

 

Requested, Catherine A. O’Connor, Director of Engineering, GMR:GRR

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Barbara J. McGowan, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for August 11, 2022

 

Attachments