TRANSMITTAL LETTER FOR BOARD MEETING OF JANUARY 23, 2025
COMMITTEE ON ENGINEERING
Mr. Brian A. Perkovich, Executive Director
Title
Report on change orders authorized and time extensions approved by the Director of Engineering during the month of December 2024
Body
Dear Sir:
There were nine change orders approved by the Director of Engineering on contracts with a 5% contingency provision for errors and omissions and unforeseen circumstances, for an increase or decrease of $100,000.00 or less during December 2024.
There were no time extension requests approved by the Director of Engineering for December 2024.
Please advise the undersigned if additional information is required.
Respectfully Submitted, Catherine A. O’Connor, Director of Engineering, GCR
Attachments