File #: 25-0896    Version: 1
Type: Agenda Item Status: Adopted
File created: 11/21/2025 In control: Procurement Committee
On agenda: 12/4/2025 Final action: 12/4/2025
Title: Authority to increase Contract 18-148-3P Digester Rehabilitation and Gas Piping Replacement - Phase II, Stickney Water Reclamation Plant, to IHC Construction Companies, LLC in an amount of $328,180.44, from an amount of $52,823,481.22, to an amount not to exceed $53,151,661.66, Account 401-50000-645750, Purchase Order 4000106
Attachments: 1. Change Order Log - Purchase Order 4000106.pdf

TRANSMITTAL LETTER FOR BOARD MEETING OF DECEMBER 4, 2025

 

COMMITTEE ON PROCUREMENT

 

Mr. John P. Murray, Executive Director

 

Title

Authority to increase Contract 18-148-3P Digester Rehabilitation and Gas Piping Replacement - Phase II, Stickney Water Reclamation Plant, to IHC Construction Companies, LLC in an amount of $328,180.44, from an amount of $52,823,481.22, to an amount not to exceed $53,151,661.66, Account 401-50000-645750, Purchase Order 4000106

Body

 

Dear Sir:

 

On November 16, 2023, the Board of Commissioners authorized the Director of Procurement and Materials Management to award Contract 18-148-3P Digester Rehabilitation and Gas Piping Replacement - Phase II, Stickney Water Reclamation Plant, to IHC Construction Companies, LLC, in an amount not to exceed $52,360,000.00, plus a five (5) percent allowance for change orders in an amount of $2,618,000.00, for a total amount not to exceed $54,978,000.00. The scheduled contract completion date is May 21, 2030.

 

As of November 21, 2025, the attached list of change orders has been approved.

 

Original Contract Amount                     $52,360,000.00

Date of Board Approval                     11/16/2023

Cumulative Change Order (11/21/2025)                     $463,481.22

% Change of Original Contract Value                     0.89%

Current Contract Value                     $52,823,481.22

Requested Increase                     $328,180.44

New Contract Value                     $53,151,661.66

% Change of Current Contract Value                     0.62%

Total % of Change of Original Contract Value                     1.51%

 

The Engineer has determined that certain revisions are required to the original scope of work for replacing a total of twenty-four control stations and motorized actuator components for the Digester Feed and Draw Valves in each of the three Digester Chambers A, B, and C in order to allow for compliance with a hazardous classified area installation. The revisions are necessary since the replacement of the control station and actuators were not shown correctly to be explosion proof rated for all three Digester Chambers under the subject contract. The contractor submitted cost proposal (CO-20) for an extra in the amount of $344,965.56 and a credit in the amount of $16,785.12, for a net extra in the amount of $328,180.44. The Engineer reviewed the proposal, found it to be reasonable, and stated via correspondence CO20, that the Engineering Department would recommend its approval.

 

This change order is in compliance with the Illinois Criminal Code since the change is due to circumstances not reasonably foreseeable at the time the contract was signed and is in the best interest of the District.

 

It is hereby recommended that the Board of Commissioners authorize the Director of Procurement and Materials Management to execute a change order to increase Contract 18-148-3P in an amount of $328,180.44 (0.62% of the current contract value), from an amount of $52,823,481.22, to an amount not to exceed $53,151,661.66.

 

Funds are available in Account 401-50000-645750

 

Requested, Catherine A. O’Connor, Director of Engineering, CS:NBP

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Precious Brady-Davis, Chairperson Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for December 4, 2025

 