TRANSMITTAL LETTER FOR BOARD MEETING OF APRIL 2, 2026
COMMITTEE ON PROCUREMENT
Mr. John P. Murray, Executive Director
Title
Authority to advertise Contract 26-025-1H Furnish and Deliver Stem Gate Valves to Various Locations for a One (1) Year Period, estimated cost $108,000.00, Account 101-20000-623090
Body
Dear Sir:
Contract documents and specifications have been prepared to furnish and deliver stem gate valves, beginning approximately June 1, 2026 and ending May 31, 2027.
The purpose of this contract is to furnish and deliver stem gate valves to the District’s storerooms to maintain sufficient inventory levels, which are required for the day-to-day operational needs of the District.
The estimated cost of this contract is $108,000.00.
No bid deposit is required for this contract.
The Multi-Project Labor Agreement (MPLA) is not applicable to this contract because it does not fall under the provisions of the MPLA.
The Affirmative Action Ordinance, Revised Appendix D and Appendix V will not be included in this contract because it is a furnish and deliver contract with no sub-contracting opportunities.
The tentative schedule for this contract is as follows:
Advertise April 8, 2026
Bid Opening April 21, 2026
Award May 21, 2026
Completion May 31, 2027
Funds are available in Accounts 101-20000-623090.
In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 26-025-1H.
Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management, DAL:SEB:MS:sk
Respectfully Submitted, Precious Brady-Davis, Chairperson Committee on Procurement