File #: 24-0267    Version: 1
Type: Agenda Item Status: Adopted
File created: 4/4/2024 In control: Procurement Committee
On agenda: 4/18/2024 Final action: 4/18/2024
Title: Authority to advertise Contract 24-695-21, Truck Scale Replacement at Various Locations, Groups A, B and C, estimated cost $850,000.00, Accounts 201-50000-645750, Requisition 1615890
Attachments: 1. Contract 24-695-21 Affirmative Action Goals Report - Groups A, B and C

TRANSMITTAL LETTER FOR BOARD MEETING OF APRIL 18, 2024

 

COMMITTEE ON PROCUREMENT

 

Mr. Brian A. Perkovich, Executive Director

 

Title

Authority to advertise Contract 24-695-21, Truck Scale Replacement at Various Locations, Groups A, B and C, estimated cost $850,000.00, Accounts 201-50000-645750, Requisition 1615890

Body

 

Dear Sir:

 

Contract documents and specifications have been prepared for Contract 24-695-21, Truck Scale Replacement at Various Locations, Groups A, B and C, at the request of the Maintenance and Operations Department.

 

The purpose of this contract is to replace truck scales at the Stickney Water Reclamation Plant, the Lawndale Avenue Solids Management Area, and at the Calumet Solids Management Area. Work under this contract will include demolition and removal of the existing scales, and installation of new scales. There will be three groups: Group A for SWRP, Group B for LASMA and Group C for CALSMA. Separate contracts could be awarded for each group.

 

The estimated cost for this contract is $850,000.00. The estimated 2024 and 2025 expenditures are $600,000.00 and $250,000.00, respectively.

 

The Multi-Project Labor Agreement (MPLA) will be included in this contract.

 

The Revised Appendix D and Appendix V will not be included in this contract due to an insufficient number of MBE/WBE/VBE firms available that can perform the requested services.

 

The tentative schedule for this contract is as follows:

Advertise                     June 5, 2024

Bid Opening                     June 25, 2024

Award                     July 11, 2024

Completion                      December 31, 2025

 

Funds are available in 2024 in Account 201-50000-645750. Funds for the subsequent year, 2025, are contingent upon the Board of Commissioners’ approval of the District’s budget for that year.

 

It is estimated this contract will employ approximately 5 to 10 personnel at any given time.

 

In view of the foregoing, it is recommended that the Director of Procurement and Materials Management be authorized to advertise Contract 24-695-21.

 

Requested, John P. Murray, Director of Maintenance and Operations, EJS:JS:SH:JR:SSG

Recommended, Darlene A. LoCascio, Director of Procurement and Materials Management

Respectfully Submitted, Marcelino Garcia, Chairman Committee on Procurement

Disposition of this agenda item will be documented in the official Regular Board Meeting Minutes of the Board of Commissioners for April 18, 2024

 